Power Generation

Performance Statistics

In terms of operations, NTPC has always been considerably above the national average.

NTPC Operating Performance PFL of NTPC Stations Vs All India

The table below shows the detailed operational performance of coal and Gas based stations over the years.

OPERATIONAL PERFORMANCE OF COAL & GAS BASED NTPC STATIONS
  Gross Generation (BU)
(COAL & GAS)
PLF (%)
(Coal Stations)
Availability Factor (%)
(Coal Stations)
2014-15 241.139 80.23 88.27
2013-14 233.269 81.50 90.32
2012-13 232.00 83.08 90.20
2011-12 222.07 85.00 89.73
2010-11 220.54 88.29 91.62
2009-10 218.84 90.81 91.76
2008-09 206.94 91.14 92.47
2007-08 200.86 92.24 92.12
2006-07 188.67 89.43 90.09
2005-06 170.88 87.52 89.91
2004-05 159.11 87.51 91.20
2003-04 149.16 84.40 88.79
2002-03 140.86 83.57 88.70
2001-02 133.20 81.11 89.09
2000-01 130.154 81.80 88.54
1999-00 118.70 80.39 90.06
1998-99 109.50 76.60 89.36